[Status: Backburner ⏳] Allow Subtasks to Update Start and End Dates of Parent Tasks

I think this is somewhere else in the community, but when I posted something else as a suggestion in the regular community area, I was asked to place my suggestion (Dependencies in the Table View) here in the Product Feedback section.

 

It would be helpful to have a setting to allow subtasks to drive the dates for the parent tasks.  Right now it's manual.  There are some who prefer it that way, and some who do not, so it would be nice to be able to set that on a per-project basis.

Upvote 400
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
183 comments

Yeah, this is ridiculous. Such a basic feature, that would make user's lives so much easier any they won't do it.

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

I agree Ben Newman - but we'll just be told it is in their backlog...... since 2017! 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hey folks! 😊 I see how helpful it would be to have subtasks update the start and end dates of parent tasks—definitely a great value addition. However, after checking with the product team, this isn’t planned at the moment. We’ll continue to share feedback from this thread with our product team and check for updates in the coming months. 👍🏽

Basudha Sakshyarika Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Basudha Sakshyarika Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: [Status: Backburner ⏳] Allow Subtasks to Update Start and End Dates of Parent Tasks
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post