Workload: Support of multiple sources / scope folder

Hi,

i would like to request a feature request for workload charts that allow to define multiple projects/folder as source for the workload chart.

Problem: At the moment, it is only possible to define a single project/folder in "Workload chart scope" for a workload chart. For us, it is required to include multiple projects into one workload chart.

 

Hochstimmen 12
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
2 Kommentare

If you leave the scope blank (empty) then it will pull from all the spaces in the account. That may be too much, but that is what I do. Anything that is from a space I am not part of is still accounted for and shows hatched instead of coloured

I agree that pulling from multiple projects/folders/spaces would be helpful.

 

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Hey Marco Eberl! Thank you for the feedback. I will pass it on to the product team for consideration. 👍🏽
 
As a workaround, you can create a new folder and tag all necessary projects or folders into this. This tagged folder can then be used as the scope for the workload chart. It will allow you to effectively include multiple projects or folders in a single workload chart. Let me know if this helps! 😊

Basudha Sakshyarika Community Team at Wrike Wrike Product Manager Werden Sie ein Wrike-Experte mit Wrike Discover

Basudha Sakshyarika Wrike Team member Werden Sie ein Wrike-Experte mit Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Workload: Support of multiple sources / scope folder
[this list is visible for admins and agents only]

Oben

Bevorstehende Live-Sitzungen

Haben Sie nicht gefunden, wonach Sie gesucht haben? Neuen Beitrag schreiben