Tasks showing outside of projects
Hi, for some reason when i am on timeline view I am seeing tasks outside of the projects, I need help to work out how to allocate them properly.
Es sieht so aus, als hätten wir die übersetzte Seite, nach der Sie suchen, nicht, aber wir haben andere Inhalte auf Englisch und bieten Unterstützung in Englisch.
Wobei können wir Ihnen helfen?
Lernen. Teilen. Diskutieren.
Hi, for some reason when i am on timeline view I am seeing tasks outside of the projects, I need help to work out how to allocate them properly.
Folllowing List for Post: Tasks showing outside of projects
[this list is visible for admins and agents only]
Hi Nick, can you let me know if the tasks are subtasks? The easy way to tell is to click on the task and see if there's a task name listed above the task title's name.
If the tasks are subtasks, then they will only appear under the appropriate Project if their parent task also shows up on the Timeline View (try checking the applied filters to make sure the parent tasks show up). If you always want subtasks to show up under the appropriate Project, you can also convert the subtask's ghost tag into a real tag.