Subtract working days only in a formula

3件のコメント

  • Spot On! 👍 Innovative Approach 💡 Stellar Advice 💪
    Avatar
    Hugh

    Hi Jay Ahluwalia, welcome to the Community!

    This is a very interesting question - could you share some more details around how you are doing this currently? I'll see whether I'll be able to help, it might be a good idea to ask our Advanced support for advice. I can raise a ticket for you from here 😊

    Let me know what you think, looking forward to learn more on what you're trying to achieve! 

    Hugh Community Team at Wrike 💡Learn about Wrike’s killer features and best practices with our Online Training Webinars

    これは役に立ちますか? 0
    コメントアクション Permalink
  • Spot On! 👍 Innovative Approach 💡 Stellar Advice 💪
    Avatar
    Jay Ahluwalia

    Hi Hugh, this would be great. We are trying to implement our shipping project plan in Wrike. So if a customer asks for an item on Wed and it take us 5 days, we have added a custom date column (Wed Date - 5) hoping that it tells us to start the job on the previous Wed (5 working days) and not Sat (5 days). Then we have a calendar showing timeline between start date and due date. This would be very helpful to us.  I am sure it would be very helpful to your other users also. Thanks   

    これは役に立ちますか? 0
    コメントアクション Permalink
  • Spot On! 👍 Innovative Approach 💡 Stellar Advice 💪
    Avatar
    Hugh

    Hi Jay! I understand what you mean now.

    When are you setting up your tasks and choosing dates, be sure to select the "working days only" option in the date view. Then, for a custom field, create a field titled "Custom Date" and set it up as a Formula custom field. If your formula is [Due Date]-[Duration], it will give you a date in your work schedule that will give you a starting date for the task!

    Hope this helped! If you have any other questions let me know 😊

    Hugh Community Team at Wrike 💡Learn about Wrike’s killer features and best practices with our Online Training Webinars

    これは役に立ちますか? 0
    コメントアクション Permalink

サインインしてコメントを残してください。

Folllowing List for Post: Subtract working days only in a formula
[this list is visible for admins and agents only]

Community

Welcome 🖖

Hi there! 🙂 Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome 🖖 Have you checked out this week's Release Notes yet?

Hey! 👋 Curious about something? Visit How To to search and ask the Community for answers.

Welcome! 👋 Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.