reporting of tasks done
Hi all ! I'm Fabrice from France .....😁
Question about tasks done : imagine i have a task planned from 21 to 22nd of october
The task is done later than it has been planned : began on 22 and finished on 23rd
Is it possible to get a report that will show me that this task is finished later than it should have been
Thanks in advance
Hi Fabrice!
One way you could view all of this information in a report would be to use Filters and Grouping. With Filters, you can choose which columns appear in your Report. In your case, I would recommend choosing Start Date, Due Date, and Completed Date.
Then you can group your tasks by the date they were completed by. This way, you can see when a task was started, it's due date, and which day it was actually completed all in one place!
If you have any other questions let me know!
thanks a lot Hugh
I'll try this very soon
👍