Dependencies moving other tasks

Can you have a dependency and have it not change the connected tasks dates when you adjust or move one of the tasks?

help.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1件のコメント

Hi Haley, happy to see you on Wrike Community 🙂

When you reschedule a task with dependencies, all dependent tasks are automatically rescheduled, this is by design. At the same time, you can shift the dependency chain to preserve the gaps between tasks when you reschedule tasks in this way. Please let me know if that can help you 🙏