When a red line appears on the gantt chart it means the task is appearing before its dependency. Is there a way to auto adjust this so that the timeline runs correctly?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1件のコメント
Hi Alex, welcome to Wrike Community 🙂
Could you please specify the red line that you mention - there's a red vertical line indicating today's date and date constraints that are represented by a solid vertical lines in front of the Task. 
Get back to me here, I'll be happy to help 🙌
 

Lisa Community Team at Wrike Wrike Product Manager Wrike DiscoverでWrikeの専門家になりましょう

Lisa Wrike Team member Wrike DiscoverでWrikeの専門家になりましょう

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: When a red line appears on the gantt chart it means the task is appearing before its dependency. Is there a way to auto adjust this so that the timeline runs correctly?
[this list is visible for admins and agents only]