Setting dependencies in template tasks
Hi,
does anyone know if it's possible to retain the dependencies in a template task without having any dates (ie. backlogged)?
Cheers,
TC
どのようなことでお手伝いできますか?
学ぶ。 共有する。 議論する。
Hi,
does anyone know if it's possible to retain the dependencies in a template task without having any dates (ie. backlogged)?
Cheers,
TC
Folllowing List for Post: Setting dependencies in template tasks
[this list is visible for admins and agents only]
I made a template to see what happens. To be clear, the dependencies would be backlogged, under the main task. The main task would have a date, right?
I created the Dependencies, but once i backlogged the sub-tasks, they were no longer dependent, see below:
I then, manually keyed in a dependent task, as shown below, but Wrike auto assigned a date to it at that point.
It looks like backlogging will not work. 😞
I would also like to know if this is possible.
Hi Aza Issifu! It's not currently possible to have dependencies between tasks without dates. Please consider upvoting this Product Feedback suggestion 👍