How to hide completed tasks in List view?
Hello,
I would like to be able to see only the active tasks in list view. How can I do that?
Thanks.
Alina
どのようなことでお手伝いできますか?
学ぶ。 共有する。 議論する。
Hello,
I would like to be able to see only the active tasks in list view. How can I do that?
Thanks.
Alina
Folllowing List for Post: How to hide completed tasks in List view?
[this list is visible for admins and agents only]
Hi Alina, you'll see a little filter icon above the list view you can see the Status above the tasks. Click here and it will show you Workflows and Status. You can then define what Status tasks you see 👍
Hello Stephen,
Is there a way to hide the completed tasks to not see them anymore. I do not want to delete them though.
When I go to a folder and use the filter to just see the active tasks and then move to another folder/proyect the filter doesn't stay in place if I go back to the first folder I applied the filter to.
Please let me know if this is possible.
Thank you
Claudia
Hi Claudia Samanez [8534], welcome to the Community, happy to see you here! 🙂
You could create an Archive folder; in this folder, you could re-create your folder structure and move certain tasks to the archive. Can this help?
Lisa Community Team at Wrike Wrike Product Manager Wrike DiscoverでWrikeの専門家になりましょう
Lisa Wrike Team member Wrike DiscoverでWrikeの専門家になりましょう
Hello Lisa,
It did helped. Thank you!
Claudia
Happy to hear that, Claudia Samanez [8534]! 🙂 Please let me know if you need help with anything else!
mdr
Lisa Community Team at Wrike Wrike Product Manager Wrike DiscoverでWrikeの専門家になりましょう
Lisa Wrike Team member Wrike DiscoverでWrikeの専門家になりましょう
Hello, is there a way to simply set a task to "hide" after being changed to Completed in the workflow?
Welcome to the Community Kimberly Milliken 🙂 You can use filters to hide all completed tasks 👍
Lisa Community Team at Wrike Wrike Product Manager Wrike DiscoverでWrikeの専門家になりましょう
Lisa Wrike Team member Wrike DiscoverでWrikeの専門家になりましょう