How to incorporate wait time into task start / end date?
Any idea how can I incorporate wait time into task schedule? For example, my task #99 (4 work hours) is dependent on completion of task #98, but the estimated wait time in queue is 10 days.
In MS Project I would set #99 predecessor as 98FS+10d, but this formula doesn't seem to be supported by Wrike. Adding "fake" tasks (wait time) makes no sense as it will impact the reporting.
Thoughts?
Thank you,
J.
Do you use templates to create these tasks within a folder or project? If so then you may want to check out this post.
https://help.wrike.com/hc/en-us/community/posts/360013608834-Set-up-task-to-start-30-days-after-another-task
Hope it helps.
-Ryan
@Jacek Ryan's post is awesome! If you would also like to +1 Megan's request that would help provide our Product Team with a lot of helpful information.