Is it possible to make a task dependent on both a predecessor and a successor, so that the task moves AND changes duration based on changes to it predecessor and successor?
I can add the dependencies to both, but it does not follow both (the way I do it at least).
Any input to this?
Best regards, Morten
Example
1: Task A
2: Task B - dependencies: 1FS +7 & 3FF -7
3: Task C