I have created a blueprint but cannot figure out how to make the parent task with 2 subtasks recurring. Whenever I set up the recurrence, it only does the parent task. How do I use the blueprint to automatically create the parent task + 2 subtasks quarterly?

Thank you!

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1件のコメント

Katie Johnson - unfortunately this doesn't seem possible at the moment. The FAQs on recurrent tasks, says sub-tasks aren't included in recurrent tasks. https://help.wrike.com/hc/en-us/articles/1500005121021-Recurrent-Tasks

I can't come up with any workarounds that I like. One possible workaround would be to use checkboxes in the description of the recurrent task (but this would only work for simple tasks and it doesn't assign them). 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: How to set up a reoccurring bluprint?
[this list is visible for admins and agents only]

トップ
Didn’t find what you were looking for? Write new post