Gantt Chart and Predecessors

Good morning. When I have a project, as an example, that has 50 tasks, Let's say task (line item) number is 5.  Task #12 shows #5 is its predecessors, FS. When I delete or add another task, my predecessor is now a different line item # and I have to review all tasks again that have predecessors and update with the new line item #. Am I doing something wrong?

 

0
1件のコメント
Spot On Innovative Approach Stellar Advice
Avatar

Hi Marilyn Ehlebracht,

Thank you for your question!

When a task's line position changes on the Gantt chart, for example when you change the sorting of the chart, the predecessor column automatically updates to reflect the change. Take a look at this series of screenshots to see what I mean. Changing the sorting will change the line position of the tasks, but the dependencies stay the same and the predecessor column adjusts automatically:

​​Please give it a try and let us know what you think 😊

Aaron K. Community Team at Wrike Wrike Product Manager Learn about Wrike’s killer features and best practices with our Online Training Webinars

Aaron K. Wrike Team member Learn about Wrike’s killer features and best practices with our Online Training Webinars