Start to Finish option

Is there a way to base a start and end date off of the end date of a project.  For example:  We know that 6 weeks prior to a launch we have to start working on marketing collateral.  Is there a way to reflect that in the Wrike timeline?  I see there is finish to finish and finish to start (most popular), but I would like a start to finish SF option.  

 

Please let me know if there are any questions.

 

Thank you,

Megan

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1件のコメント
Avatar
Stephanie Westbrook

Hi again Megan 👋

Yes, we do have a start to finish option for dependencies, but I think you also need to be able to set lead and lag time between the tasks (you mention that the task needs to be done 6wks prior to launch). Currently, you can't set lead and lag times within Wrike, but it is something that the team wants to work on. It's also something that Megan and many others have requested and if you could add a +1 to that thread, that would be great. 

Based on current functionality, one workaround that may work is to create a "dummy" task that spans 6 weeks and use that to preserve the gap between time you have to start working on marketing collateral and launch. 

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Start to Finish option
[this list is visible for admins and agents only]

トップ

今後のライブセッション

お探しのものが見つかりませんか? 新しい投稿を作成する