Start to Finish option
Is there a way to base a start and end date off of the end date of a project. For example: We know that 6 weeks prior to a launch we have to start working on marketing collateral. Is there a way to reflect that in the Wrike timeline? I see there is finish to finish and finish to start (most popular), but I would like a start to finish SF option.
Please let me know if there are any questions.
Thank you,
Megan
Hi again Megan 👋
Yes, we do have a start to finish option for dependencies, but I think you also need to be able to set lead and lag time between the tasks (you mention that the task needs to be done 6wks prior to launch). Currently, you can't set lead and lag times within Wrike, but it is something that the team wants to work on. It's also something that Megan and many others have requested and if you could add a +1 to that thread, that would be great.
Based on current functionality, one workaround that may work is to create a "dummy" task that spans 6 weeks and use that to preserve the gap between time you have to start working on marketing collateral and launch.