Postponing a task that is dependent on other
Good afternoon.
Is there any way to link two tasks that are scheduled with a certain period of distance of each other in a way that postponing the first one, the second is also postponed.
For example: "Task one was supposed to be completed on January 10th and task two starts on January 20th. Can I postpone task one to January 15th and task two automatically be rescheduled to January 25th?"
Thanks and Regards.
Hi Luan, thanks for asking this question here! It's possible to reschedule dependent tasks and preserve their scheduling gaps on the Timeline View, as long as they are connected by a milestone task. To do this:
Happy to answer any other questions about this! :)
Thank you, Anastasia.
That's exactly what I wanted, it was really helpful!
Regards
Luan, great to hear that! Let me know if there's anything else I can help with. :)
In the animated image above, it looks like when you drag the milestone, the space between preceding tasks is not preserved. Is that correct?
Hi @Claire, thanks for reaching out 🙂
There's no gap between task1 and task2 there, only Saturday and Sunday which are usually non-working days. When you shift a Dependency chain, all gaps between tasks are preserved.
Please let me know if you'd like to discuss this further 👍