make dependencies of closed tasks
i need to beable to make a task depended of a close status task.
when i search for a dependency i see no status closed tasks. but i need to..
now i need to work arround it by chaching the status en then add and then close again
it takes extra work.
Hi Jan, thanks for reaching out here! Just to make sure I understood correctly: are you looking for a way to add dependencies to tasks which have already been completed? If so, it's possible to do this by making sure the filtering criteria on the Timeline View is set to show tasks with any status. Once these tasks are shown, dependencies can be added in the usual way:
Does this help? Happy to answer any other questions!