Need a little help please.   🙂  For some reason when I have subtasks and change the date for one of them it does not update the date for the main task.  Is there a way to correct this?  I'm usually in Gannt or Table view.

Thank you for your help,

Joe

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1件のコメント

Welcome to the Community Joe Kniffen 👋

Per this Knowledge Base article, there are some exceptions to the alignment rule - if they are milestones or a part of dependencies. Can you please let me know if your case is covered by these exceptions? 

 