Stretch hours over a Multi-Day project
Wrike request:
Have ability to have a Start and an End time to a project and assign the number of hours the project will take and have those hours stretched across the Start/End times.
For example: I have a flyer to make, and i assign it to Employee #1 on October 30th, and I know it will take that person 10 work hours to do it. I want first draft within a month (November 30th). I don’t have a specific day or time i want them to do it, i just need it to be done by Nov30th.
Current situation: I can only assign the task to a specific day, or assign it over multiple days, which is usually the Due Date. However i know they will work on it before the due date, but i look at their Workload, all those hours will just be shown on the due date.
The Goal: To assign a project with a specific amount of work hours over a longer work period. This allows me to get a weekly or even monthly snapshot of how many Work-Hours they are assigned to
Hi Paul! Thank you for sharing your use case. The Workload View and Effort Allocation are great, but I think viewing and saving the data as a Table Report or through the Table View are actually the best options in this case. To do this:
This can all be replicated in the Reporting section and saved, so that you would have quick and easy access to the data. Would this help?
I think what Paul ment was to have a time frame and assign the maximum hours for that time frame. I can imagine the following: If the hours are exeeded, the worker get's an alert and the numbers in the table turn to red. Even better: The table shows planned hours and used hours.
We have a similar issue: a staff member can be working on multiple tasks at the same time, for which the time period is longer than the amount of work the task requires.
For example, they may have two tasks which take one-and-a-half days each, both which can be done within a 'window' of five days. We do this to allow the staff member flexibility in their working time and to allow enough time for meetings, etc to be held comfortably. So let's add add another task on the first day of the week which takes one day.
To a human scheduler – and the person doing the work – this is four days work, over a period of five days, which is a weekly task-to-time ratio of 80%.
To Wrike this is one day with a 130% tasking, one day with a 30% tasking and three days at 0% tasking.
For allocation to be successful, it needs to look at the allocated time and available time across ALL currently live tasks and tell you whether there is enough time in total for the task to be done – just as the human scheduler does automatically in our example – but I don't see a way of doing that right now in Wrike. Anyone?
We have a similar situation, as would many, it seems. A four-day task that you have a month to complete and so might work at it in various windows of time over the month. Tricky. Interested in how others schedule a multitude of tasks like this.
Microsoft Project does it perfect. As always, Microsoft Project is the oldest project management software on the market. They have addressed a lot of issues other pm software will encounter in the future. But it is expensive and not so flexible.
@Mark, @Nikolaus, @Paul, thanks for adding information here, would definitely love to hear how other teams handle scheduling like this right now (apart from the suggestion Anastasia made above). For now, I'll also go ahead and add a +1 for each of you for some more flexibility around scheduling on the Workload View.
I used to love Microsoft Project until I found Wrike... Team Collaboration on a MPP file was horrible! With that said, MS project definitely has some features Wrike doesn't and sophisticated resource load balancing calculations at the daily level is one of them. But what I love about Wrike is that I can click up and down in my project hierarchy to do this same resource load balancing in a visual GANT format. That was never possible with MPP. So in order to get the "top level" view, I always had to keep massive MPP files with everything in it and all these linked MPP sub-project files that always got corrupted because someone changed things. Wrike lets you do load balancing at individual project levels and at high top levels easily by clicking up through your project hierarchy.
Anyway, with that said, I'm not sure I understand Paul's question; sorry. Allocation in Wrike assumes fixed allocation across the task duration, correct? So isn't this the same thing you are describing? If I have a 4 day task that has a 5 day duration, this shows up as 80% across the 5 days in workload view and I can shift/adjust as necessary to load balance at any level. If it's completed at day 4, then the 80% allocation is removed and I'm on to something else. And if I know there is a specific task/milestone that's occurring as part of that task (like the "first draft due" example above), I make sure to track it as a separate task (or sub-task) and put a end to end relationship on it so I know it's due date is fixed to the due date of the parent task (and shifts with it). If I'm being granular on the allocation tracking, I subtract the "first draft" task allocation from the main/original task and put it on the new task (e.g. 40% on first draft, 40% on the main task). Otherwise I just put 0% allocation on the first draft since I'm just looking at it as a milestone and not tracking effort hours for that milestone separately from the main task.
Anyway,with that said, the Wrike enhancements that I think would make this load balancing process much better are the following:
Jeni, thank you for commenting on this! I've submitted your feedback to our Product Team. Reading about your workflow and how you use the allocation feature was fantastic, and I'm sure others will find this explanation useful. Thank you again for taking the time to share all of these details!