get notification when two previous tasks are done
Hi!,
I would like to know if its possible to connect 2 tasks to a next task in the Gantt Chart?
So in my example I want the electrical empoloye and the Mechanical employe working at the same time at different tasks. and when there both done there will be a notification to the next employe for him to start on the next task.
In other words, I would like to connect 2 tasks on to the next one. Both tasks need to be done before the next responsible person wil get a notification.
Hi Etiënne Geleijnse, welcome to the Community!
To answer your first question, if I understand you correctly, you'd like to create 2 predecessor tasks. You can do it by creating two FS dependencies linked to the same task.
I suggest creating an automation rule - if all predecessors change status to "completed" then notify the assignee. Another solution is to create a rule for each task - if a task is completed, mention the user.
Please let me know if you have any questions 🙋🏻♀️
Cansu Community Team at Wrike Wrike Product Manager En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online
Cansu Wrike Team member En savoir plus sur les fonctionalités et les meilleures pratiques grace à nos Webinaires online