Moving tasks from 'Next sprint' to 'Backlog'.
Hi,
I added a task to 'Next Spring', now I want to move to 'Backlog'. Couldn't find anything in the UI to achieve this. Is there a way?
Thanks,
Vinay.
Il semble que nous n'ayons pas la page traduite que vous cherchez, mais nous avons d'autres contenus en anglais et offrons une assistance en anglais.
Que pouvons-nous faire pour vous ?
Apprendre. Partager. Discuter.
Hi,
I added a task to 'Next Spring', now I want to move to 'Backlog'. Couldn't find anything in the UI to achieve this. Is there a way?
Thanks,
Vinay.
Folllowing List for Post: Moving tasks from 'Next sprint' to 'Backlog'.
[this list is visible for admins and agents only]
Hi Vinay, there's two kinds of a backlog. One could be part of your workflow and is simple a Status and this depends on the Custom Status and Workflow you're using.
Like the below where Backlogged is a Status option:
The second kind of backlog is when you schedule a task to be backlog so it doesn't show up on the Timeline view. You can convert a task to backlogged and here's how.
Let me know if these options help! 🙌