Define weekend days as working days

Does anyone know if and where I can define weekend days (Saturday & Sunday) as working days? So that it is possible to start and end projects on weekend days? 

 

Thanks for your help. 

Michael

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
5 commentaires

Hi Michael Schweiß - This is something an admin can do by defining a new "Work Schedule" in the settings. :) Here's a quick article explaining more - https://help.wrike.com/hc/en-us/articles/1500005123581-Creating-Custom-Work-Schedule

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Your account admin or owner can set Work Schedules for the organization:

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Is the checkbox for 'working days only' unchecked within the date selector of the project/task?  If this is checked on then things can't be scheduled on the weekend but if it's unchecked you can schedule on the weekend.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

I am an admin, can i change the work week for a specific project?  For example, one project that needs to add Saturdays to its work week. 

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Omar A. Morales,
no you can't change work week only for a specific project, instead you can remove on tasks the checkbox Working days only if saturday is a day off.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Define weekend days as working days
[this list is visible for admins and agents only]

Haut de la page
Didn’t find what you were looking for? Write new post