HOW TO MAKE RECURRENCES OF TWO OR MORE ACTIVITIES WITH DEPENDENCES ?

Dears,

i would like to create a mountly routine of two activities in one dependent from the other with this rule: act1 1 day before act2

the best solution could be create a main task with these two subtask (act1 and act2), create dependence and duplicate tha main task with internal structure of subtask. i saw it is not possible

Is there another system ? 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comentario

Hi nicola mariucci, welcome to the Community! 🙂

Because dependencies aren't preserved when you make tasks recurrent, I'd suggest this:

1) Create two tasks for act1 and act2

2) Make them both recurrent and create a certain amount of tasks upfront

3) Open them in Gantt Chart and add dependencies for them

You will then have those two monthly tasks with dependencies. Please let me know if you have any further questions, I'll be happy to discuss 👍

Lisa Community Team at Wrike Wrike Product Manager Conviértete en un experto en Wrike con Wrike Discover

Lisa Wrike Team member Conviértete en un experto en Wrike con Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: HOW TO MAKE RECURRENCES OF TWO OR MORE ACTIVITIES WITH DEPENDENCES ?
[this list is visible for admins and agents only]

Superior

Próximas sesiones en vivo

¿No encontraste lo que buscabas? Escribir nueva publicación