Hello,
I work in the Middle East and have customers both in the Middle East region as well as Europe. We regularly create project plans and share these with our customers.
As the work week in the Middle East is Sun-Thurs, we have some projects plans that are Sun-Thurs and some that are Mon-Fri (for Europe based customers).
Is it possible to set different work weeks for different project plans instead of on the account level? At the moment we are manually changing the work week every time we need to switch between project plans for different customers
Hi Tania Mammen! You can create different work schedules and assign them to different users in your account. You can do this in the Account Management menu.
Hope this helps!
Hi @...! Thanks for your reply. Currently we are using Wrike Professional, so I it appears this option is not available to us.
Also, I'm looking more for the ability to have different work schedules for different projects as opposed to assigning them based on the user. Perhaps this would be additional functionality?
Thanks nonetheless for your response.
Hi Tania Mammen! That particular feature is not currently possible, but your suggestion has been passed on to the Product team 😊