I'm looking for an easier way to organize my projects with dependencies. I'm working with a product development launch timeline and currently have it organized that each seasonal launch is a project which consists of the timeline, in the form of milestones. Each development is a sub-project within the launch project, which consists of tasks that are dependencies for the timeline milestones.
I find myself getting overwhelmed by the repeated tasks that each development requires. I've mapped out a quick idea of my structuring. My goal is to keep each development's progress and details documented but also see the launch's progress as a whole, as my team approaches the milestones along the launch timeline.
Spring 2019 Launch (project)
Create Drawings 11-9-18 (milestone)
Production Models 12-14-18 (milestone)
Photo Samples 1-4-18 (milestone)
Product 1 (sub-project)
Create Drawing- Product 1 (task, dependency for Create Drawings milestone)
Production Model- Product 1 (task, dependency for Production Models milestone)
Photo Sample- Product 1 (task, dependency for Photo Samples milestone)
Product 2 (sub-project)
Create Drawing- Product 2 (task, dependency for Create Drawings milestone)
Production Model- Product 2 (task, dependency for Production Models milestone)
Photo Sample- Product 2 (task, dependency for Photo Samples milestone)
I don't doubt there's a much easier way to achieve this so I'm open to hearing drastic restructuring ideas, though I'm hoping a small tweak is all that's necessary.
Lisa Community Team at Wrike Wrike Product Manager Conviértete en un experto en Wrike con Wrike Discover