Add Author As Assignee in Blueprint
Hey,
I think a really handy feature for Blueprints would be the ability to add the "author" as the assignee. Right now, we’re using automations as a workaround because the author is usually the project owner (and also the stakeholder/SME), so they need to be involved in several key steps throughout the project.
How do you all manage adding the author or SME to the necessary tasks when a new project is created? Would love to hear how others are handling this!
Hey Kelly St.Cyr!
We created an empty job role called "Requester" and have set up an automation so that when a new task (or project) is created, to:
a) Add author on tasks that have Requester assigned
b) Remove Requester job role
Agree with your point - if it was something that was pre-established and possible in blueprints, or even in request forms, it would make our list of automations a little less chaotic :)
I'm also utilizing automations to assign the author to a projects' tasks. Our workaround is to leave the task unassigned in the blueprint and then the automation is:
Apply rule to: Task
When: new item is created
Condition: Assignee is unassigned
Change assignee to: Item author
Is this similar to the automations you currently have in place?
Anna Giacobbe that is a great workaround. Thank you! I am hoping they can work this into their updates in the near future to make it easier without the need for automations!