Report with Project Owners AND Task Owners

We have four different project managers on our team.  As a PM team, we go through the entire list to determine whose projects are on track, behind, etc. and we're currently having to pull two different reports (one project-based and one task-based) to get the report that we actually want. I'd love to see a filter on our task reports to also include the project owner(s) so that we have a holistic view of who is responsible for each project from a project owner level in addition to the tasks that are housed within that project and the individuals who are responsible for those.

Votar positivamente 6
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
4 comentarios

Thank you for submitting your feedback Kristen Gundersen! I understand it may not be perfect, but have you tried using the New Table view for this purpose? 

Lisa Community Team at Wrike Wrike Product Manager Conviértete en un experto en Wrike con Wrike Discover

Lisa Wrike Team member Conviértete en un experto en Wrike con Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Lisa, I have not. I've been in contact with Kevin Vega who told us that what we were looking for was not possible unless we wanted to create a custom field for project owners that is then assigned to each task within a project. 

I just took a look at the new table view and it could potentially work, but we need a holistic view of our space with report of only active or on/hold projects that can also be exported. Is this possible?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

More interaction between Projects and the Tasks within them would be incredibly helpful for us in a number of different ways--both with viewing information and especially with Automation.

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hey folks! Here's how it can look like with the new Table view:

I have a space for projects and can see them with tasks and assignees for both projects and tasks. I can apply filters to both tasks and projects:

It's also possible to export the view to Excel:

Please let me know if this could work for you! 

Lisa Community Team at Wrike Wrike Product Manager Conviértete en un experto en Wrike con Wrike Discover

Lisa Wrike Team member Conviértete en un experto en Wrike con Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Report with Project Owners AND Task Owners
[this list is visible for admins and agents only]

Superior

Próximas sesiones en vivo

¿No encontraste lo que buscabas? Escribir nueva publicación