Booked Effort Rollup in Folders and Spaces

Booked Effort rollup is currently unavailable from the Table View of a Folder or Space like many other custom fields. For many other fields, you are able to “enable [rollup] for all projects" within a space or folder (which cuts down on manual effort). For Booked Effort, if your projects are stored within a folder or space, you have to manually enable booked effort on all of your projects.

  • I have been given the explanation that this is because "Booked Effort" is linked to projects directly and it is expected that roll up would only be available for projects. While I was given the explanation that "Other custom fields... are based on tasks. And in this case the rollup is available for all items (folders and projects) where those tasks are stored."
  • It would also make just as much sense to say: "Booked Effort is based on projects. And in this case the rollup is available for all items (folders and spaces) where those projects are stored."
Hochstimmen 0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
4 Kommentare

The documentation here seems to suggest you should be able to do this based on the "Tip" section. 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Cansu

Hi Ian Kizer, welcome to the Community and thank you for posting. I see you've had a conversation with our Support agents on this question. To provide the answer to other Community members that might visit this thread, bookings are linked to projects directly, it is expected that the roll-up for them is available for projects only.     

Please don't hesitate to let us know if we can help you with anything else. 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi @....Thanks! 

  • Do you know of any other way to default Booked Effort roll-ups for all projects @ the space or folder level?
  • I think there was a little confusion from the Support team, that we wanted project custom fields to roll-up beyond the project (we just want to enable Booked Effort Roll Up for all projects within a folder).
    -We're trying to get out of manually clicking into every project created in a specific folder on a weekly basis to enable Booked Effort roll-up using a Created Date report.
    -I was also given the reasoning that "Other custom fields, such as "Time spent" are based on tasks. And in this case the rollup is available for all items (folders and projects) where those tasks are stored."
    -From my perspective here, projects, like tasks, are often stored in folders--in addition to other projects. 

    Thanks!

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Cansu

Hi Ian Kizer, I see that our Support team is working with our Product team on this clarification. They will be reaching out as soon as they have an update. Please let me know if I can help you with anything else🙋🏻‍♀️

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Booked Effort Rollup in Folders and Spaces
[this list is visible for admins and agents only]

Oben

Bevorstehende Live-Sitzungen

Haben Sie nicht gefunden, wonach Sie gesucht haben? Neuen Beitrag schreiben