Convert Milestone to Task - mass edit
Does anyone know an easy way to convert 500+ milestones to regular task? We can do a mass edit to milestone but can't go back... any work arounds or just a manual edit?
Es sieht so aus, als hätten wir die übersetzte Seite, nach der Sie suchen, nicht, aber wir haben andere Inhalte auf Englisch und bieten Unterstützung in Englisch.
Wobei können wir Ihnen helfen?
Lernen. Teilen. Diskutieren.
Does anyone know an easy way to convert 500+ milestones to regular task? We can do a mass edit to milestone but can't go back... any work arounds or just a manual edit?
Folllowing List for Post: Convert Milestone to Task - mass edit
[this list is visible for admins and agents only]
Hi Norma Hansen, thank you for reaching out!
It is possible to mass edit milestones with Advanced rescheduling options - you can clear the dates for them or setting the start and due dates:
Can this help?
Lisa Community Team at Wrike Wrike Product Manager Werde ein Wrike-Experte mit Wrike Discover
Lisa Wrike Team member Werde ein Wrike-Experte mit Wrike Discover
How do I do the opposite... mass edit to convert tasks to milestones?
We have had the same problem since the milestones in the calendar were shown as diamonds. We don't like that at all and so I now have to convert more than 1000 milestones into regular tasks. Deleting the date first and then redefining it doesn't work in mass edit because the milestones don't have the same date. I just miss the function of converting many milestones into regular tasks at once, as it already exists in the other direction. Converting several regular tasks into milestones works perfectly.
Hi Martina Kock 👋
Thank you for taking the time to share your feedback and explain your use-case. I have forwarded your comment to the relevant product team for their visibility.
Rohan V Community Team at Wrike Wrike Product Manager Werden Sie ein Wrike-Experte mit Wrike Discover
Rohan V Wrike Team member Werden Sie ein Wrike-Experte mit Wrike Discover