Duration of Tasks
Hi
Just wanted to inquire if the was any intention of allowing for a task duration of less then a day as this limits the amount of team organising that can be achieved for short term projects.
Thanks
Es sieht so aus, als hätten wir die übersetzte Seite, nach der Sie suchen, nicht, aber wir haben andere Inhalte auf Englisch und bieten Unterstützung in Englisch.
Wobei können wir Ihnen helfen?
Lernen. Teilen. Diskutieren.
Hi
Just wanted to inquire if the was any intention of allowing for a task duration of less then a day as this limits the amount of team organising that can be achieved for short term projects.
Thanks
Folllowing List for Post: Duration of Tasks
[this list is visible for admins and agents only]
Yes please! We often have tasks that needs to be done "before lunchtime". And another task that will have to be done in the afternoon is sometimes dependent on that. I would love to have days in my company but we are often talking of hours when things has to be ready.
Hi Patrick Dyett, Anders Kilbrandt! It's possible to set the start date and due date for your task and/or specify duration in hours, minutes, or days:
Please let me know if that helps!
Lisa Community Team at Wrike Wrike Product Manager Werde ein Wrike-Experte mit Wrike Discover
Lisa Wrike Team member Werde ein Wrike-Experte mit Wrike Discover