Interrupting Tasks

Hi,

Iam searching for the possibility to interrupt tasks.

In MS Project there was the possibility to split a task into two and then to shoft the second part some days to the future. That is always very usefull if you have to shift a person to an other project for a week. It makes nearly no work, it is clear what happened and you can react very quickly.

In Wrike I could not find such possibility up to now.

Is there any way of doing this?

mdr

Upvote 6
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
7 Kommentare
Avatar
Hugh

Hi Sven Passinger,

One workaround for this could be to create subtasks within these tasks to show the different parts of each one. This way, you could create individual deadlines for each of these parts, and reassign them as you so wish.

Let me know if this helped! If you have any other questions, feel free to reach out at any time.

mdr

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

In principal that would be a possibility, but it makes unnecessary work.

We are already planing only two week tasks and we do not want to go on daily task planning. Unfortunately we have a very flexible buiseness to satisfy our customers, so that sometimes after one week working on a task is is interrupted for a week or two and then continued. If we want now to make it with subtask we have to make, due to the fact that this happens surprisingly while already some work is in the task, two new sub-tasks (one for the work already done and one for the new work), delete the effort from the task and put it to the sub-tasks seperately. That is quiet a lot of work for the project manager (if he has more than one supporting department (design, electronics, ...) on the task it makes really work.

So in principal yes it would be possible. In reality I do not think that we like it, as it costs money for this additional work.

mdr

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Hugh

Hey Sven Passinger,

Thank you for providing this additional detail about this suggestion.

If you'd like, I can move this idea to the Product Feedback section? This way, your feedback will be shared with the Product team, and other Community members will be able to show their support for this.

mdr

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Yes please move it to the Product Feedback section..

I think it could be a simple and very helpful feature for Wrike.

mdr

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Hugh

Hi Sven Passinger,

Just moved this thread to the Product Feedback section! If you need anything else, be sure to let me know.

mdr

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hello 

Has there been any update to spliting a task as is done in MS Project?

Regards,

Al

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Alberto Alvarez, welcome to Wrike Community 👋

No updates at the moment. Please be sure to upvote the main post if you haven't yet as votes matter 🙂

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Interrupting Tasks
[this list is visible for admins and agents only]

Nach oben
Didn’t find what you were looking for? Write new post