How can I move subtasks out from underneath a parent task?

I want to move subtasks out from underneath a parent task and into a top-level folder. (see image) The only way I can figure out how to do this is to duplicate tasks. 

If I do mass edit and click move to demand gen folder...nothing moves out from under the incorrect parent task (OD Webinar)

Any thoughts?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
6 Kommentare

Hi Devin!

To do this, you would use the "Detach" function. Right-click on the task you want to detach in the list view and select the detach command. Keep in mind though that when you detach it from the parent task, it might also detach it from the folder! If the folder is slightly grayed out, that means it's in that folder because the parent task is. Just be sure to manually tag the task before you detach it and you're golden!

Folder grayed out (task is in the folder because the parent task is)

Not grayed out (task is directly tagged to this folder)

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Ah, got it....thank you! :-) Such a simple fix. 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Devin, if you're in the Gantt view, select the task then hit "Ctrl + ["  (control key plus left bracket).  Conversely, you can use "Ctrl + ]" (control key plus right bracket) to turn a task into a sub-task of a task at an equivalent level above.

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Where do Unassigned(detached) Tasks go?  They are not searchable and they do not go to the REcycle Bin.  My Companies Parent Folder has, since the new layout showing PERSONAL, disappeared.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

@Jason Hi, thanks for reaching out! I'm raising a Support ticket for you, someone from the team will be in touch soon about this 👍

Lisa Community Team at Wrike Wrike Product Manager Werde ein Wrike-Experte mit Wrike Discover

Lisa Wrike Team member Werde ein Wrike-Experte mit Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

That worked.  You are awesome! Thank you.

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: How can I move subtasks out from underneath a parent task?
[this list is visible for admins and agents only]

Oben

Bevorstehende Live-Sitzungen

Haben Sie nicht gefunden, wonach Sie gesucht haben? Neuen Beitrag schreiben