how do I exclude weekends from the work week?
currently when setting tasks they are running through the weekends. I'd like to exclude weekends to only count Monday to Friday as work days.
Es sieht so aus, als hätten wir die übersetzte Seite, nach der Sie suchen, nicht, aber wir haben andere Inhalte auf Englisch und bieten Unterstützung in Englisch.
Wobei können wir Ihnen helfen?
Lernen. Teilen. Diskutieren.
currently when setting tasks they are running through the weekends. I'd like to exclude weekends to only count Monday to Friday as work days.
Folllowing List for Post: how do I exclude weekends from the work week?
[this list is visible for admins and agents only]
Hi Shane,
This setting is under Account Management! I have attached a screenshot.
Click on "Edit workweek" to be able to change the workweek dates! I am one of the company account administrators, so I am not sure if this ability is specifically for admins or all users.
Hope this helps 😄
although the Task seem to run through the weekend, it actually doesn't - the duration is 6 days, because Wrike only counts the working days (Mon - Fri) that were set by the account Admin. If I wanted to take the weekend days into account, I'd check the "work on weekends" box. You can learn more about Work Schedules on our Help Center.