Constraining a task date to facilitate the Gantt chart view

Hi all,

I'm wondering if there's a way to add date constraints to tasks without having to move the task.  I'd like to include dependencies in the Gantt chart, but also have the ability to prevent all tasks from being automatically pushed forward if I move help.wrike.com/hc/en-us/articles/209604249-Date-Constraints-on-the-Gantt-Chartof the preceding tasks forward.  With such a feature, I'd be able to see if my dependencies are broken, rather than having Wrike fix them automatically without my knowledge.  Any thoughts?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 Kommentar
Avatar
Stephen

Hi Andrei, there's no direct way to do this as the tasks will shift to align with the constraint. As a workaround, you can set the Status to a 'backlog' Status. This might work for your process. It won't force the task to move even if there's broken dependency relationship.

Give it a go and let me know we're on the right track. Happy to continue discussing.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Constraining a task date to facilitate the Gantt chart view
[this list is visible for admins and agents only]

Oben

Bevorstehende Live-Sitzungen

Haben Sie nicht gefunden, wonach Sie gesucht haben? Neuen Beitrag schreiben