Darker line in Gantt chart task - what does it indicate?

What does this line mean?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 Kommentar

Hi Jennifer,

These are Date Constraints. Date constraints signal the earliest date that a task can begin. Once a date constraint is in place, the task cannot be automatically rescheduled to a date prior to the constraint. A date constraint is automatically added to the dependent task when you reschedule it to a different start date.