How to incorporate wait time into task start / end date?

Any idea how can I incorporate wait time into task schedule? For example, my task #99 (4 work hours) is dependent on completion of task #98, but the estimated wait time in queue is 10 days.

In MS Project I would set #99 predecessor as 98FS+10d, but this formula doesn't seem to be supported by Wrike. Adding "fake" tasks (wait time) makes no sense as it will impact the reporting.

Thoughts? 

Thank you,

J.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
2 Kommentare

Do you use templates to create these tasks within a folder or project? If so then you may want to check out this post.

https://help.wrike.com/hc/en-us/community/posts/360013608834-Set-up-task-to-start-30-days-after-another-task

Hope it helps.

-Ryan

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Stephanie Westbrook

@Jacek Ryan's post is awesome! If you would also like to +1 Megan's request that would help provide our Product Team with a lot of helpful information.  

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: How to incorporate wait time into task start / end date?
[this list is visible for admins and agents only]

Oben

Bevorstehende Live-Sitzungen

Haben Sie nicht gefunden, wonach Sie gesucht haben? Neuen Beitrag schreiben