Viewing the workload chart for collaborators (limited users)

Hello,

Am I correct that collaborators not only cannot use the workload chart, but also cannot view it? It would be really handy if also collaborators who only execute tasks can see the workload overview for their team (for during team meetings).

Does anybody use an alternative workaround to visualize the work of the department for collaborators?

with kind regards, 

Simone

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
3 Kommentare
Hi Simone Darphorn 👋  You're right. Collaborators cannot access or view the Workload charts. However, here are a couple of workarounds that might help:

1. Timeline View: Collaborators can be filtered by assignee in the Timeline view, allowing you to see their tasks and manage their workload visually.

2. Reports and Dashboards: Another option is to create reports or dashboards that can be shared with collaborators. While collaborators cannot access dashboards directly, reports can be shared with them, allowing them to see a summary of tasks and their statuses.

Please do let us know if you require further assistance, I’d be happy to raise a Support Ticket on your behalf. Thanks!

Rohan V Community Team at Wrike Wrike Product Manager Erfahren Sie mehr über Wrikes leistungsstarke Funktionen und lernen Sie Anwendungsbeispiele kennen

Rohan V Wrike Team member Erfahren Sie mehr über Wrikes leistungsstarke Funktionen und lernen Sie Anwendungsbeispiele kennen

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Dear Rohan,

The timeline view is the Gant view, right? It is only for a specific project so that does not show a planboard of the activities of someone's department. 

I'm now using the calendar so a team member can at least see his own activities over time. But that does unfortunately not show any effort allocated to the corresponding to the task. 

Report can only give a list of the tasks and statuses, but this is already captured in the My-To-Do, right?

regards, Simone

 

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Hi Simone Darphorn, I apologize for the inconvenience caused, and thank you for taking the time to explain. I’m looping in our support expert here. If there's any alternative workaround, they will be able to assist you. Thanks again.

Rohan V Community Team at Wrike Wrike Product Manager Erfahren Sie mehr über Wrikes leistungsstarke Funktionen und lernen Sie Anwendungsbeispiele kennen

Rohan V Wrike Team member Erfahren Sie mehr über Wrikes leistungsstarke Funktionen und lernen Sie Anwendungsbeispiele kennen

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Viewing the workload chart for collaborators (limited users)
[this list is visible for admins and agents only]

Nach oben
Didn’t find what you were looking for? Write new post