Command to include a range of predecessor tasks
Hello,
I have a task to which I want to include a range of predecessors (from task 7 to 24 for example), is there a way to do this without having to include each task in the ‘predecessors’ box one by one?
It would be very useful to have a way to be able to type this range without having to include all the numbers of the different tasks one by one.
Thanks in advance
Hey Asier Zuñiga! Welcome to the Wrike Community, and thank you for sharing your feedback!
At the moment, predecessors (or successors) need to be added individually. However, your idea of allowing input for a range is a great suggestion. I’ve forwarded it to the product team. 🚀
I'd also recommend checking out this post which explains how the Product Feedback forum works. Please, also feel free to visit our New to Community forum to get the most out of your experience with Wrike. 🙂
Basudha Sakshyarika Community Team at Wrike Wrike Product Manager Werden Sie ein Wrike-Experte mit Wrike Discover
Basudha Sakshyarika Wrike Team member Werden Sie ein Wrike-Experte mit Wrike Discover
We would also like to add a range to the predecessor...as I need to go from 3 to 77...that is alot of numbers to type
Welcome to the Community, Richard Wind, and thanks for sharing your feedback. I’ve forwarded your response to our Product team 🙂
Rohan V Community Team at Wrike Wrike Product Manager Werden Sie ein Wrike-Experte mit Wrike Discover