Date constraints should be visible in table view
Date constraints serve a useful purpose in scheduling, but if you are in the table view you have no idea you may have _inadvertently_ created one. In Wrike there is NO WAY to do this unless you go to the Gantt Chart view. There, either the bold date constraint line or the Start Constraint column can give you that information. However, many of us like to work primarily in the Table view. In that view there is _no indication_ that a date has been fixed. If you update predecessors, you will assume the dates recalculate, but they will not.
There should be some visual indication that a date has been fixed and is not floating per its dependencies without leaving the table view.
An earlier post mentioned this some time back but it does not appear to have been actioned.