Building Dashboard or Report from cross-tagged tasks

Hi - My team manages projects that are cross-functional. We have a number of projects in Wrike that are cross tagged for a status update. 

I'd like to create a report or dashboard that could shows all tasks that are tagged with for status update and then organized by the project. 

Could I do a screenshare/call to help me determine if there's a solve?

Thanks, Megan

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 Kommentar
Avatar
Stephen

Hi Megan, thanks for your post and welcome to the Community 👋
 
Reporting on status update requests is not currently possible but thanks for sharing the idea here. You may also be interested in voting on this post from Travis about tracking requests in the comments section.
 
As a workaround, for now, you could add a checkbox Custom Field, named 'Requested Status Update', for example. 
 
You could then check/uncheck this when you've sent an update request. Once an update is received the checkbox can be unchecked. 
 
I understand, this is a little manual and will require your team to uncheck the Custom Field when an update has been provided. However, using this process means you can use the Report Builder to create see all tasks that have this Custom Field ticked.
 
I'm interested to hear your thoughts on the above and if I've misunderstood your query, please let me know 🙂
0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Building Dashboard or Report from cross-tagged tasks
[this list is visible for admins and agents only]

Oben

Bevorstehende Live-Sitzungen

Haben Sie nicht gefunden, wonach Sie gesucht haben? Neuen Beitrag schreiben