How do I print the subtasks in the timeline snapshot view?

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 Kommentar
Avatar
Stephanie Westbrook

Hi Joan, thanks for your post and welcome to the Community! You should be able to see subtasks on the snapshot. Are you able to see the subtasks on the Timeline before you create the snapshot? If not, there are two quick things to check: 1) do the subtasks have scheduled dates (they need dates to be visible on the Timeline) and 2) do the subtasks match the filter settings? For example, if you're filtering for active tasks the subtasks should have an active status. 
 
Let me know if either of those helps and we'll go from there if not. 