When I create a schedule from scratch, I create the tasks first. Theses tasks don't show in the Gantt chart until I put a date in each task. It's would be much more easier if I could see the task in the Gantt chart before a select the right date. This way, I could move the task at the right place (date) and create dependency faster.
Thanks
Hi Manuel, thanks for posting on the Community! The Timeline View is date based, so there's no way and place to display a task which isn't scheduled. It's possible, however, to create tasks right on the Timeline by clicking on an empty space while holding the shift key. This allows you to quickly create and schedule tasks right from this view, and instantly connect these tasks with dependencies. Happy to answer any questions about this! :)