Custom Item Types - Dates do Not rollup on 'Project' level anymore
It is no longer possible to enable dates rollup on task due dates, this is very problematic. We really miss this feature.
Die von Ihnen gesuchte Seite ist nicht in übersetzter Form vorhanden, wir verfügen jedoch über andere Inhalte in deutscher Sprache und bieten deutschsprachigen Support an.
Wie können wir helfen?
Learn. Share. Discuss.
It is no longer possible to enable dates rollup on task due dates, this is very problematic. We really miss this feature.
Folllowing List for Post: Custom Item Types - Dates do Not rollup on 'Project' level anymore
[this list is visible for admins and agents only]
This as well is on the planning according to the answers on my post. It is indeed a handy feature that would be great too see in custom item types as well!
FYI, the post, with feedback from Wrike, can be found here: https://help.wrike.com/hc/en-us/community/posts/10599974405015-Feedback-concerning-Custom-Item-Types-
Yeah its causing huge issues for us at the moment. We are considering removing custom item types until its fixed because manually updating project dates is just crazy
Thanks a lot for posting the link to the other post here, Sammy 🙌
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover