change dates on sub-tasks that are same within a project but under a different main task

I have same sub-tasks for various tasks within the project but need to have different dates depending on the main task.  When changing the date on my sub-task - it changes the date on all sub-task with the same name

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Комментариев: 3

Hi Glenda Brungardt, am I right in understanding that you use the same subtask rather than different subtasks with a similar name? To confirm that, please check the task ID. Is it the same for all the items? 

In this case, I suggest duplicating the subtask so that you can edit the items separately and set different dates for them. Hope it helps!

Lisa K. Community Team at Wrike Wrike Product Manager Станьте экспертом в Wrike с Wrike Discover

Lisa K. Wrike Team member Станьте экспертом в Wrike с Wrike Discover

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thank you - will take this info and see if it solves my issue

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Please let us know how it goes Glenda Brungardt 🤗

Lisa Community Team at Wrike Wrike Product Manager Станьте экспертом Wrike с Wrike Discover

Lisa Wrike Team member Станьте экспертом Wrike с Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: change dates on sub-tasks that are same within a project but under a different main task
[this list is visible for admins and agents only]

Верх

Предстоящие сессии в прямом эфире

Не нашли то, что искали? Написать новое сообщение