Set exact dates using predessors

Is there a way to set exact dates for tasks using predecessors? I have a 1st task that all other tasks are dependent on and must occur on an exact number of days after it. By using dependencies all dates will shift when I move the 1st task. However it is still possible to move an individual task to a later date which is not allowed and could easily be done by mistake

0
2 commenti
Spot On Innovative Approach Stellar Advice

Hi Tiffany,

if the duedate of a task must not be changed automaticaly, you have to define it as a milestone. This is simply done by removing the start-date.

0
Azioni per commenti Permalink
Spot On Innovative Approach Stellar Advice

This doesn't seem work as I want the option to move the 1st task (upon which everything is dependent) and have the following tasks move to the exact number of days after the 1st task (which works). The problem is that is not possible to "lock" the task to e.g 2 days after the 1st task. It is just a minimum of 2 days after the first task which means it can be moved to 3, 4, 5 etc. days after

0
Azioni per commenti Permalink