Incorrect date alignment when duplicating project
I have noticed that when I duplicate a project that ends on a Thursday and the new project ends on a Tuesday, the date alignment is off. It will make tasks that were on two different days of the week due on the same day if the new date alignment caused one to (almost) fall on a weekend. We have our Wrike set up to not schedule tasks on weekends.
Is there a way to make it so Wrike knows to push tasks back past the weekend to the previous business day? I wind up having to manually adjust those dates myself and it is time consuming. The only fix that I could come up with is to have separate templates for the same project that all land on different days of the week. That seems like a lot of extra work?
Any suggestions would be most appreciated!
Ginger