Re-align due dates when making a project timeframe shorter

We have a blueprint project set up to span a 5 week timeframe. There are 5 tasks in the blueprint, each set up with start and end dates. 

Sometimes a project will come in that takes less time than the 5 weeks built into the blueprint. What do I need to do so that after I launch the blueprint then I shorten the project timeframe all the tasks within the project re-align accordingly? 

I have attempted to use the date-rollup feature, it does not work at all. I have created the blueprint with all 5 tasks being subtasks, does not re-align properly. I have made the final task a milestone and changed that date to be shorter than the blueprint timeframe, hit Apply when prompted to re-align all the subtask due dates - nothing happened. I've also tested the blueprint with and without the tasks being dependent. Nothing is working to re-align the dates correctly if I need to shorten the project timeframe.

I do not want to have to tell my team to manually adjust each tasks date range.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 commento

Hi Maegen Maher
can you manage different blueprints based on durations? You can create, for example, 3 different blueprint with 5 weeks, 4 weeks, 3 weeks.
So you can choice the best that works for each case.

Otherwise you can do something similar by using API.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Re-align due dates when making a project timeframe shorter
[this list is visible for admins and agents only]

Su
Didn’t find what you were looking for? Write new post