Create a report to show tasks where flexible effort assignment has exceeded the initial plan
Hi,
We use the flexible effort type across our projects to allow our users to plan their days more easily.
This can create a problem though where a user might add more time to a task than was originally assigned. For example, there may be a task with 20 hours planned, of which 20 hours are assigned to a User1 for delivery over 5 days. When the task is first assigned Wrike will assign 4 hours per day. However, User1 might then go into their workload and change the amount of assigned time per day to the following:
Day 1: 5 hours
Day2: 5 hours
Day3: 8 hours
Day4:5 hours
Day5: 5 hours
Without realising it, they have now assigned themselves to 28 hours even though the task was only originally scheduled for 20.
Wrike already detects this happening and formats the effort column for that task in red in table view. This is very helpful but it's very time consuming to go through every project and look for that red highlight. I'd therefore like to create a dashboard or a WA report that will show only those tasks where this is a problem (i.e. only show those tasks that are highlighted in red in the table view).
Is this possible?
Hi Phil Taylor! Your Wrike Analyze Master Jedi is here:)
Herine Community Team at Wrike Wrike Product Manager Conosci le straordinarie funzionalità di Wrike e le best practices
Herine Wrike Team member Conosci le straordinarie funzionalità di Wrike e le best practices
Hello again Herine! You truly are a Master Jedi! I'll build the report just as you suggest. Thanks for being your awesome self again :-)