Turning booked effort into task effort
Hi,
We're starting to use booked effort to reserve employee time for projects that are specced only at a high level at this point.
My question is, what's the usual process to "convert" booked effort to task effort?
Say we have a project that we know is going to take about 100hours to deliver. I have booked two people to the project at 50 hours each and this is appearing in their workload plans. All good.
At some point in the future we write the detailed proposal for the project which contains a list of all the individual tasks and their dates and times. I assign the two people that were booked to the project to these tasks and now their workload plan is showing them as over resourced. Do I simply delete the booked effort or is there a more intelligent way of consuming the booked time and transforming it into task time? Am I overthinking this?
Thanks!
Phil Taylor firstly, well done on expanding your use of Wrike and trying on new features. Good news is that you have already figured it out: it is just a matter of deleting the booking.
A couple of additional pointers
I hope this clears some of your questions.
Miron Mizrahi Community Team at Wrike Wrike Product Manager Conosci le straordinarie funzionalità di Wrike e le best practices
Miron Mizrahi Wrike Team member Conosci le straordinarie funzionalità di Wrike e le best practices