Table View: adding Dependancies
I am able to add a column and name it dependencies but for some reason, it is not pulling them from the project. Help :)
help.wrike.com/hc/en-us/articles/210323525-Table-View-Overview
Il semble que la page que vous recherchez n'existe pas dans votre langue. Mais nous proposons d'autres contenus en français ainsi qu'une assistance en français.
En quoi pouvons-nous vous aider ?
Learn. Share. Discuss.
I am able to add a column and name it dependencies but for some reason, it is not pulling them from the project. Help :)
help.wrike.com/hc/en-us/articles/210323525-Table-View-Overview
Folllowing List for Post: Table View: adding Dependancies
[this list is visible for admins and agents only]
Hey Svetlana, happy to see you on the Community 🙂
Dependencies are shown in the Gantt Chart View: on its table and timeline portions. Table View doesn't show task dependencies.
Please let me know if you have any other questions 🙌
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
HI Lisa, so it sounds like i cannot add that column to the Table view, correct?
Svetlana, that's correct, dependencies are only shown on the Gantt Chart's table and timeline. That said, you can still create a custom column in the Table View and call it "Dependent task", for example, but then you'll need to add them manually. I'm very interested to hear how you are planning to use dependencies and why the Gantt Chart's table seems not to be enough?
Please get back to me here
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
HI Lisa,
Sometimes the Gantt view might be overwhelming to some so i walk them through the list on the table. The way I build my timelines are in order of tasks and labeled as such, 01, 02, A, B, etc... so to some, seeing a list is easier to follow than a bunch of lines and connections...It's just another way of me walking people through the timeline. Ideally, if i add this column in table, it would be great if it can auto populate, just a request. I might be the only one though :)
thx for asking.
Svetlana
Hey Svetlana, thanks for describing your use-case 🙂
You are certainly not the only one, please check out this Product Feedback thread. You can upvote the suggestion, and I'll update the thread when I have some news 👍
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover