Darker line in Gantt chart task - what does it indicate?
What does this line mean?

Il semble que nous n'ayons pas la page traduite que vous cherchez, mais nous avons d'autres contenus en anglais et offrons une assistance en anglais.
Que pouvons-nous faire pour vous ?
Apprendre. Partager. Discuter.
What does this line mean?

Folllowing List for Post: Darker line in Gantt chart task - what does it indicate?
[this list is visible for admins and agents only]
Hi Jennifer,
These are Date Constraints. Date constraints signal the earliest date that a task can begin. Once a date constraint is in place, the task cannot be automatically rescheduled to a date prior to the constraint. A date constraint is automatically added to the dependent task when you reschedule it to a different start date.